Most of what is written about campsite planning is about tents and tourers, and most of it leans on the temporary-use rules: 28 days a year for almost any land, 60 days for a campsite under the 2023 permitted development right. Pods, cabins and huts are different, and the difference costs people a season when they find out late. This article is about structures: what needs permission, when a hut on wheels escapes it, what the council will actually look at, and how to get through the process in time to open.
It covers England in detail; Wales and Scotland have their own rules, which are noted at the end. None of it is legal advice, and the one thing every council agrees on is that a conversation with its planning officer before you buy anything is the cheapest step in the whole project.
Why the 28-day and 60-day rules do not help
The temporary-use rights work because the land is unchanged. A tent goes up, a tourer parks, and at the end of the stay the field is a field again. Planning law calls that a change of use for a limited period, and it tolerates it.
A pod, a cabin or a lodge is a different thing in law: it is operational development, the creation of a building. Fixing it to a base, plumbing it in and wiring it up makes it part of the land. Operational development needs planning permission regardless of how many days a year anyone sleeps in it, and the 60-day campsite right explicitly excludes it: the right allows tents, motorhomes and touring caravans with movable facilities, not units that stay.
So the honest starting point for pods and cabins is that you will need a planning application. The rest of this article is about making that application succeed.
The caravan loophole, and its limits
A shepherd's hut on wheels, a towable pod or a static unit can fall within the legal definition of a caravan: a structure designed for human habitation that can be moved from place to place by towing or on a vehicle, within the size limits (20 metres long, 6.8 metres wide and 3.05 metres internal height). A caravan is not a building, so placing one on land is not operational development.
That is useful, but it is narrower than the hut sellers suggest, for three reasons.
- The land use still needs permission. Using land as a caravan site for paying guests is a change of use and, separately, requires a caravan site licence from the council under the Caravan Sites and Control of Development Act 1960. The 28-day rule and the exempted club schemes are the main routes around that, and both have limits that rule out a year-round glamping business.
- It must actually be movable. A hut that has been plumbed to a soakaway, skirted, decked around and never moved in three years will be treated by most councils as a structure. Keep the wheels on and the services detachable if you are relying on the definition.
- The works around it are development. A hardstanding, a deck, a hot tub base, a gravel track and a shower cabin all need permission in their own right. The hut being a caravan does not cover the things you build to serve it.
Change of use on a farm
Most glamping sites start on farms, and the first assumption to drop is that agricultural permitted development rights help. They cover barns, tracks and buildings for farming. Holiday accommodation is a change of use from agriculture to a tourism use, full stop.
The good news is that councils like farm diversification. National planning policy in England expressly supports rural tourism and the diversification of farm businesses, and a well-prepared application for a handful of units on a working farm is one of the more sympathetically received things a rural planning officer sees. If you are also thinking about pitches, running a campsite on agricultural land covers that side.
What the council will look at
Every application is judged on the same handful of things. Deal with them before you apply and the decision is mostly made.
- Access and highways. Can guests get in and out safely? A junction onto a fast lane with poor visibility sinks more rural applications than anything else. The highways team will be consulted and their word carries.
- Neighbours. Noise, headlights, hot tubs at midnight. Site the units away from other houses, show where screening goes, and talk to the neighbours before the letters land.
- Landscape and character. In a National Park, an AONB (now a National Landscape) or the Green Belt the bar is higher, not impossible. Timber-clad units, dark colours, no floodlights and planting that already exists help.
- Drainage and sewage. Where does the shower water go? A treatment plant or a connection to mains drainage, with a drainage strategy, is expected. A soakaway on clay is not.
- Ecology. Bats, newts, nesting birds and hedgerows. A preliminary ecological appraisal is often requested and is cheap compared with a refusal. Since 2024 most applications in England also need to show biodiversity net gain, though small sites may be exempt or able to deliver it on site.
- Flood risk. Units in a flood zone need a flood risk assessment and will often be refused outright for overnight accommodation.
- Scale and season. Five units on a 200-acre farm reads as diversification. Twenty units on a smallholding reads as a holiday park. Councils also commonly attach a condition limiting occupancy to holiday use and preventing anyone living in a unit permanently.
How to apply
- Pre-application advice. Most councils offer it for a fee of a few hundred pounds. You get a written view on whether the principle is acceptable and what the application will need. Do this before buying units.
- Surveys. Ecology, drainage, sometimes a transport statement for the access. Commission the ones the pre-app response asks for.
- The application. A full planning application for change of use and the operational development, with a site plan, unit drawings, a design and access statement and the surveys. Fees are set nationally; use the Planning Portal's calculator for the current figure.
- The decision. The statutory target is eight weeks for minor applications. In practice allow longer, and allow for a request to tweak the scheme.
- After permission. Discharge any conditions, apply for the site licence if caravans are involved, and check building regulations: a pod with a bathroom and electrics usually needs a building control sign-off even where planning was straightforward.
From first conversation to decision, four to six months is normal. Applying in the autumn to open the following summer is the usual rhythm, and it is why so many first seasons start late.
If you already have units on the ground
Plenty of sites grew without permission and now want to regularise. A retrospective application is the honest route and is judged on the same merits as a fresh one. A lawful development certificate is possible where the use has gone on continuously for ten years, but you will need evidence: bookings, bank records, photographs with dates. Councils can serve an enforcement notice on an unauthorised use at any point before that, so it is a gamble, not a strategy.
Wales and Scotland
- Wales has the 28-day temporary-use right but did not adopt the 60-day campsite right. Operational development and change of use rules work much as in England; apply through the local authority and expect similar considerations.
- Scotland has its own permitted development order with a 28-day temporary-use allowance, and caravan site licensing under the same 1960 Act. Shepherd's huts and pods there are treated along the same lines: the structure, the use and the works around it each need looking at.
Frequently asked questions
Do glamping pods need planning permission?
In almost every case, yes. A pod, cabin or lodge fixed to the ground is operational development, and letting it to paying guests is a change of use. Neither is covered by the 28-day or 60-day temporary-use rules, which exist for tents and tourers on land that is otherwise unchanged.
Does a shepherd's hut need planning permission?
A hut on wheels that fits the legal caravan definition is not a building, so placing it is not operational development. Using the land as a caravan site for paying guests still normally needs planning permission and a site licence unless an exemption applies, and councils treat a hut that is plumbed in and never moves as a structure.
Can I put glamping pods on a farm without planning permission?
No. Agricultural permitted development rights cover farming, not holiday accommodation. Glamping on a farm is a change of use from agriculture to tourism, which most councils support as diversification when access, neighbours, drainage and landscape are handled well.
How long does glamping planning permission take?
Four to six months from the first conversation to a decision is realistic: pre-application advice, surveys, the application, then the council's eight-week target, which is often exceeded. Apply in autumn to be open for the following summer.
Once the permission is in and the units are on order, the next question is what the whole thing costs to open. And when you are ready to take bookings, Campiamo's free plan handles a handful of units with no commission; set it up in a few minutes.
Ready to simplify your campsite operations?
Join campsite operators who've cut admin time by 75% and increased bookings with Campiamo's all-in-one platform.
- Online booking
- Auto payments
- Guest comms
- Live reporting